Model | Last Updated | Order Banks Open | Spec Release Anticipated Date | Pricing Release Date | Start of Production | Last Date to Submit Orders to Merchants | Build Out Date | Average Lead Time | Important Updates |
---|---|---|---|---|---|---|---|---|---|
CT4 | 2/18/25 | 4/18/24 | 4/30/24 | 4/30/24 | 6/3/24 | 2/18/25 | 2/25/25 | 10 weeks | Closed 25MY |
CT5 Non-Blackwing / Non-V Series | 2/18/25 | 3/7/24 | 3/20/24 | 3/29/24 | 5/6/24 | 2/18/25 | 2/25/25 | 9 weeks | Closed 25MY |
CT5 V series | 2/18/25 | 6/13/24 | 3/20/24 | 3/29/24 | 7/22/24 | 2/18/25 | 2/25/25 | 9 weeks | Closed 25MY |
CT5 Blackwing / V Series | 2/18/25 | TBD | 3/20/24 | 3/29/24 | TBD | 2/18/25 | 2/25/25 | 9 weeks | Closed 25MY |
Escalade LWS/SWB | 4/25/25 | 8/8/24 | 8/21/24 | 8/30/24 | 10/8/24 | 5/20/25 | 5/27/25 | 16 weeks | Closed 25MY |
Escalade IQ | 2/18/25 | 7/11/24 | 7/22/24 | 8/1/24 | 7/8/24 | 2/18/25 | 2/25/25 | 15 weeks | Closed 25MY |
Lyriq | 2/18/25 | 8/8/24 | 8/23/24 | 8/23/24 | 9/9/24 | 3/25/25 | 4/1/25 | 15 weeks | Closed 25MY |
Optiq | 2/18/25 | 8/22/24 | 8/23/24 | 8/23/24 | 10/14/24 | 5/20/25 | 5/27/25 | TBD | Closed 25MY |
XT4 | 2/18/25 | 5/16/24 | 5/17/24 | 5/17/24 | 7/30/24 | 10/24/24 | 10/31/24 | 11 weeks | Closed 25MY |
XT5 | 5/15/25 | 5/16/24 | 6/12/24 | 6/12/24 | 6/24/24 | 8/28/25 | 9/2/25 | 18 weeks | |
XT6 | 7/1/25 | 5/16/24 | 6/12/24 | 7/8/24 | 6/24/24 | 7/22/25 | 7/29/25 | 18 weeks |